What's New

ASA - 2.8.18



We are seeing more progress at Mandan’s All Seasons Arena! Progress includes beam installation, LED lighting, painting and mechanical ductwork. Starting Feb. 19, and taking about three weeks to complete, construction crews will install the volleyball and basketball standards in the ceiling and the dividers within the courts. Once this is completed, they will start installing the flooring which takes an estimated period of 5 weeks.